본문 바로가기
1/1

Selayang Hospital

사업 정보
Location Selangor 
Completion Date September / 1998 
Client Ministry of Works & Public Utilities  
Project Overview 6 buildings / 12 stories, 964 hospital beds 
Total Area 147464㎡ 

In October 1996, Ssangyong E&C received the order to construct Selayang Hospital in Malaysia together with Obayashi Corp, Japan.

As Ssangyong E&C, which was in charge of the main hospital building construction, had to build the ward with 964 beds and treatment facilities within a short construction period, it introduced the fast-track method, where design and construction are conducted simultaneously.

Also, it could finish construction within schedule, as the building was designed to be built through assembled components: The PC (pre concrete) slabs, that were perforated to reduce weight, were employed on the top of the pre-installed pillars and beams.